Offshore Project Portfolio Prioritisation

2-3 days · Designed for Boards, executives, public officials and senior managers

2-3 days EX programme focused on Offshore Project Portfolio Prioritisation, using energy-sector cases and applied decisions.

Download complete course manual (PDF)

Illustrated course presenter

YOUR AVATAR GUIDE

Learn with your course presenter

Listen to any module using the voice available on this device. Choose a module below to begin.

What you will learn

Module 1: Offshore Project Portfolio Prioritisation: Core Concepts

Learning objectives

Lessons

  1. Purpose and key terms of Offshore Project Portfolio Prioritisation: Core Concepts
  2. Systems and operating context
  3. Evidence, assumptions and decision gates
  4. Hazards, safeguards and escalation
  5. Applied case: Offshore Project Portfolio Prioritisation

Teaching notes

## Teaching notes

Core explanation. Offshore Project Portfolio Prioritisation: Core Concepts describes a practical part of Offshore Project Portfolio Prioritisation. Learners connect the principles to asset performance, people, operational risk, project value and local context.

Decision logic. Review the objective, evidence, limits, interfaces and applicable controls for offshore project portfolio prioritisation: core concepts. Decisions require current information, role-appropriate authority, competent review and documented assumptions.

Worked example. Use an applied Namibia-relevant case in which a team plans offshore project portfolio prioritisation: core concepts while balancing safety, integrity, schedule, cost, environmental protection and local capability.

Facilitator prompts. Ask learners to distinguish verified facts from assumptions, identify who has decision authority, name stop-work triggers and state what evidence could change their recommendation. Compare technical, HSE, commercial and community perspectives.

Activity. Prepare a decision brief for offshore project portfolio prioritisation: core concepts: scope, evidence, assumptions, hazards, safeguards, owner, decision gate and escalation trigger.

Model answer guide. A sound response defines scope; uses current, traceable evidence; applies approved requirements and controls; records assumptions; assigns competent owners; checks interfaces; and communicates a measurable decision with an escalation path.

Assessment evidence. Score accuracy (30%), use of evidence (20%), safeguards (20%), analysis (20%) and communication (10%).

Activity

Prepare a decision brief for offshore project portfolio prioritisation: core concepts: scope, evidence, assumptions, hazards, safeguards, owner, decision gate and escalation trigger.

Assessment

Formative: 10-question practice quiz with answer feedback

Summative: Applied decision brief or practical case assessed against the rubric; proposed pass mark 70%, subject to academic approval.

Resources

Module 2: Offshore Project Portfolio Prioritisation: Risk Controls

Learning objectives

Lessons

  1. Purpose and key terms of Offshore Project Portfolio Prioritisation: Risk Controls
  2. Systems and operating context
  3. Evidence, assumptions and decision gates
  4. Hazards, safeguards and escalation
  5. Applied case: Offshore Project Portfolio Prioritisation

Teaching notes

## Teaching notes

Core explanation. Offshore Project Portfolio Prioritisation: Risk Controls describes a practical part of Offshore Project Portfolio Prioritisation. Learners connect the principles to asset performance, people, operational risk, project value and local context.

Decision logic. Review the objective, evidence, limits, interfaces and applicable controls for offshore project portfolio prioritisation: risk controls. Decisions require current information, role-appropriate authority, competent review and documented assumptions.

Worked example. Use an applied Namibia-relevant case in which a team plans offshore project portfolio prioritisation: risk controls while balancing safety, integrity, schedule, cost, environmental protection and local capability.

Facilitator prompts. Ask learners to distinguish verified facts from assumptions, identify who has decision authority, name stop-work triggers and state what evidence could change their recommendation. Compare technical, HSE, commercial and community perspectives.

Activity. Prepare a decision brief for offshore project portfolio prioritisation: risk controls: scope, evidence, assumptions, hazards, safeguards, owner, decision gate and escalation trigger.

Model answer guide. A sound response defines scope; uses current, traceable evidence; applies approved requirements and controls; records assumptions; assigns competent owners; checks interfaces; and communicates a measurable decision with an escalation path.

Assessment evidence. Score accuracy (30%), use of evidence (20%), safeguards (20%), analysis (20%) and communication (10%).

Activity

Prepare a decision brief for offshore project portfolio prioritisation: risk controls: scope, evidence, assumptions, hazards, safeguards, owner, decision gate and escalation trigger.

Assessment

Formative: 10-question practice quiz with answer feedback

Summative: Applied decision brief or practical case assessed against the rubric; proposed pass mark 70%, subject to academic approval.

Resources

Module 3: Risk assessment and uncertainty management

Learning objectives

Lessons

  1. Purpose and key terms of Risk assessment and uncertainty management
  2. Systems and operating context
  3. Evidence, assumptions and decision gates
  4. Hazards, safeguards and escalation
  5. Applied case: Offshore Project Portfolio Prioritisation

Teaching notes

## Teaching notes

Core explanation. Define the activity and potential harm, identify hazards, evaluate existing controls, then decide further controls and ownership. A risk matrix supports prioritisation but does not prove a risk is tolerable. Include affected people and changing conditions.

Decision logic. Test whether controls are present and effective. Residual risk should be reassessed after control implementation, not merely after a promise. Escalate high-consequence uncertainty for competent review. Project risk also includes schedule, cost and opportunity effects.

Worked example. A permit lists a barrier that has not yet been installed. The claimed residual risk is premature.

Facilitator prompts. Ask learners to distinguish verified facts from assumptions, identify who has decision authority, name stop-work triggers and state what evidence could change their recommendation. Compare technical, HSE, commercial and community perspectives.

Activity. Complete a risk register with cause, event, consequence, control, owner and verification.

Model answer guide. Keep hazard and consequence distinct and require evidence before taking control credit.

Assessment evidence. Score accuracy (30%), use of evidence (20%), safeguards (20%), analysis (20%) and communication (10%).

Activity

Complete a risk register with cause, event, consequence, control, owner and verification.

Assessment

Formative: 10-question practice quiz with answer feedback

Summative: Applied decision brief or practical case assessed against the rubric; proposed pass mark 70%, subject to academic approval.

Resources

Module 4: CAPEX OPEX and estimating

Learning objectives

Lessons

  1. Purpose and key terms of CAPEX OPEX and estimating
  2. Systems and operating context
  3. Evidence, assumptions and decision gates
  4. Hazards, safeguards and escalation
  5. Applied case: Offshore Project Portfolio Prioritisation

Teaching notes

## Teaching notes

Core explanation. Capital estimates cover assets and development; operating estimates cover recurring delivery and support activities. Define scope, price basis, location, currency, schedule and exclusions before estimating. A number without its basis is difficult to review.

Decision logic. Use analogous, parametric and bottom-up methods according to data maturity. Separate base estimate, identified risk contingency and other reserves under the adopted governance. Avoid implying that contingency is spare money for scope additions.

Worked example. A fictional equipment package is 10 million and installation is estimated at 40% of equipment cost; subtotal is 14 million before other scope.

Facilitator prompts. Ask learners to distinguish verified facts from assumptions, identify who has decision authority, name stop-work triggers and state what evidence could change their recommendation. Compare technical, HSE, commercial and community perspectives.

Activity. Write an estimate basis and identify five excluded cost items.

Model answer guide. Include logistics, commissioning, taxes, spares and owner costs where appropriate; state assumptions rather than silently adding them.

Assessment evidence. Score accuracy (30%), use of evidence (20%), safeguards (20%), analysis (20%) and communication (10%).

Activity

Write an estimate basis and identify five excluded cost items.

Assessment

Formative: 10-question practice quiz with answer feedback

Summative: Applied decision brief or practical case assessed against the rubric; proposed pass mark 70%, subject to academic approval.

Resources

Module 5: Planning scheduling and critical path

Learning objectives

Lessons

  1. Purpose and key terms of Planning scheduling and critical path
  2. Systems and operating context
  3. Evidence, assumptions and decision gates
  4. Hazards, safeguards and escalation
  5. Applied case: Offshore Project Portfolio Prioritisation

Teaching notes

## Teaching notes

Core explanation. A schedule links activities through dependencies, durations, calendars and resources. Critical path identifies the longest duration path under the model's assumptions. Float is a calculated property, not spare time owned automatically by one team.

Decision logic. Validate logic before trusting dates. Resource constraints and uncertain weather windows can change the critical path. Compression may add cost or risk. State assumptions and update from actual progress rather than forcing the plan to match a desired date.

Worked example. Path A takes 3 plus 4 days; parallel path B takes 5 days. The simplified project duration is 7 days.

Facilitator prompts. Ask learners to distinguish verified facts from assumptions, identify who has decision authority, name stop-work triggers and state what evidence could change their recommendation. Compare technical, HSE, commercial and community perspectives.

Activity. Calculate duration after A's first task increases to 5 days.

Model answer guide. The A path becomes 9 days; assess downstream effects and valid recovery choices.

Assessment evidence. Score accuracy (30%), use of evidence (20%), safeguards (20%), analysis (20%) and communication (10%).

Activity

Calculate duration after A's first task increases to 5 days.

Assessment

Formative: 10-question practice quiz with answer feedback

Summative: Applied decision brief or practical case assessed against the rubric; proposed pass mark 70%, subject to academic approval.

Resources

Module 6: Offshore Project Portfolio Prioritisation: Data and Performance

Learning objectives

Lessons

  1. Purpose and key terms of Offshore Project Portfolio Prioritisation: Data and Performance
  2. Systems and operating context
  3. Evidence, assumptions and decision gates
  4. Hazards, safeguards and escalation
  5. Applied case: Offshore Project Portfolio Prioritisation

Teaching notes

## Teaching notes

Core explanation. Offshore Project Portfolio Prioritisation: Data and Performance describes a practical part of Offshore Project Portfolio Prioritisation. Learners connect the principles to asset performance, people, operational risk, project value and local context.

Decision logic. Review the objective, evidence, limits, interfaces and applicable controls for offshore project portfolio prioritisation: data and performance. Decisions require current information, role-appropriate authority, competent review and documented assumptions.

Worked example. Use an applied Namibia-relevant case in which a team plans offshore project portfolio prioritisation: data and performance while balancing safety, integrity, schedule, cost, environmental protection and local capability.

Facilitator prompts. Ask learners to distinguish verified facts from assumptions, identify who has decision authority, name stop-work triggers and state what evidence could change their recommendation. Compare technical, HSE, commercial and community perspectives.

Activity. Prepare a decision brief for offshore project portfolio prioritisation: data and performance: scope, evidence, assumptions, hazards, safeguards, owner, decision gate and escalation trigger.

Model answer guide. A sound response defines scope; uses current, traceable evidence; applies approved requirements and controls; records assumptions; assigns competent owners; checks interfaces; and communicates a measurable decision with an escalation path.

Assessment evidence. Score accuracy (30%), use of evidence (20%), safeguards (20%), analysis (20%) and communication (10%).

Activity

Prepare a decision brief for offshore project portfolio prioritisation: data and performance: scope, evidence, assumptions, hazards, safeguards, owner, decision gate and escalation trigger.

Assessment

Formative: 10-question practice quiz with answer feedback

Summative: Applied decision brief or practical case assessed against the rubric; proposed pass mark 70%, subject to academic approval.

Resources

Module 7: Offshore Project Portfolio Prioritisation: Applied Case

Learning objectives

Lessons

  1. Purpose and key terms of Offshore Project Portfolio Prioritisation: Applied Case
  2. Systems and operating context
  3. Evidence, assumptions and decision gates
  4. Hazards, safeguards and escalation
  5. Applied case: Offshore Project Portfolio Prioritisation

Teaching notes

## Teaching notes

Core explanation. Offshore Project Portfolio Prioritisation: Applied Case describes a practical part of Offshore Project Portfolio Prioritisation. Learners connect the principles to asset performance, people, operational risk, project value and local context.

Decision logic. Review the objective, evidence, limits, interfaces and applicable controls for offshore project portfolio prioritisation: applied case. Decisions require current information, role-appropriate authority, competent review and documented assumptions.

Worked example. Use an applied Namibia-relevant case in which a team plans offshore project portfolio prioritisation: applied case while balancing safety, integrity, schedule, cost, environmental protection and local capability.

Facilitator prompts. Ask learners to distinguish verified facts from assumptions, identify who has decision authority, name stop-work triggers and state what evidence could change their recommendation. Compare technical, HSE, commercial and community perspectives.

Activity. Prepare a decision brief for offshore project portfolio prioritisation: applied case: scope, evidence, assumptions, hazards, safeguards, owner, decision gate and escalation trigger.

Model answer guide. A sound response defines scope; uses current, traceable evidence; applies approved requirements and controls; records assumptions; assigns competent owners; checks interfaces; and communicates a measurable decision with an escalation path.

Assessment evidence. Score accuracy (30%), use of evidence (20%), safeguards (20%), analysis (20%) and communication (10%).

Activity

Prepare a decision brief for offshore project portfolio prioritisation: applied case: scope, evidence, assumptions, hazards, safeguards, owner, decision gate and escalation trigger.

Assessment

Formative: 10-question practice quiz with answer feedback

Summative: Applied decision brief or practical case assessed against the rubric; proposed pass mark 70%, subject to academic approval.

Resources

Module 8: Offshore Project Portfolio Prioritisation: Communication and Escalation

Learning objectives

Lessons

  1. Purpose and key terms of Offshore Project Portfolio Prioritisation: Communication and Escalation
  2. Systems and operating context
  3. Evidence, assumptions and decision gates
  4. Hazards, safeguards and escalation
  5. Applied case: Offshore Project Portfolio Prioritisation

Teaching notes

## Teaching notes

Core explanation. Offshore Project Portfolio Prioritisation: Communication and Escalation describes a practical part of Offshore Project Portfolio Prioritisation. Learners connect the principles to asset performance, people, operational risk, project value and local context.

Decision logic. Review the objective, evidence, limits, interfaces and applicable controls for offshore project portfolio prioritisation: communication and escalation. Decisions require current information, role-appropriate authority, competent review and documented assumptions.

Worked example. Use an applied Namibia-relevant case in which a team plans offshore project portfolio prioritisation: communication and escalation while balancing safety, integrity, schedule, cost, environmental protection and local capability.

Facilitator prompts. Ask learners to distinguish verified facts from assumptions, identify who has decision authority, name stop-work triggers and state what evidence could change their recommendation. Compare technical, HSE, commercial and community perspectives.

Activity. Prepare a decision brief for offshore project portfolio prioritisation: communication and escalation: scope, evidence, assumptions, hazards, safeguards, owner, decision gate and escalation trigger.

Model answer guide. A sound response defines scope; uses current, traceable evidence; applies approved requirements and controls; records assumptions; assigns competent owners; checks interfaces; and communicates a measurable decision with an escalation path.

Assessment evidence. Score accuracy (30%), use of evidence (20%), safeguards (20%), analysis (20%) and communication (10%).

Activity

Prepare a decision brief for offshore project portfolio prioritisation: communication and escalation: scope, evidence, assumptions, hazards, safeguards, owner, decision gate and escalation trigger.

Assessment

Formative: 10-question practice quiz with answer feedback

Summative: Applied decision brief or practical case assessed against the rubric; proposed pass mark 70%, subject to academic approval.

Resources

Module 9: Offshore Project Portfolio Prioritisation: Knowledge Check

Learning objectives

Lessons

  1. Purpose and key terms of Offshore Project Portfolio Prioritisation: Knowledge Check
  2. Systems and operating context
  3. Evidence, assumptions and decision gates
  4. Hazards, safeguards and escalation
  5. Applied case: Offshore Project Portfolio Prioritisation

Teaching notes

## Teaching notes

Core explanation. Offshore Project Portfolio Prioritisation: Knowledge Check describes a practical part of Offshore Project Portfolio Prioritisation. Learners connect the principles to asset performance, people, operational risk, project value and local context.

Decision logic. Review the objective, evidence, limits, interfaces and applicable controls for offshore project portfolio prioritisation: knowledge check. Decisions require current information, role-appropriate authority, competent review and documented assumptions.

Worked example. Use an applied Namibia-relevant case in which a team plans offshore project portfolio prioritisation: knowledge check while balancing safety, integrity, schedule, cost, environmental protection and local capability.

Facilitator prompts. Ask learners to distinguish verified facts from assumptions, identify who has decision authority, name stop-work triggers and state what evidence could change their recommendation. Compare technical, HSE, commercial and community perspectives.

Activity. Prepare a decision brief for offshore project portfolio prioritisation: knowledge check: scope, evidence, assumptions, hazards, safeguards, owner, decision gate and escalation trigger.

Model answer guide. A sound response defines scope; uses current, traceable evidence; applies approved requirements and controls; records assumptions; assigns competent owners; checks interfaces; and communicates a measurable decision with an escalation path.

Assessment evidence. Score accuracy (30%), use of evidence (20%), safeguards (20%), analysis (20%) and communication (10%).

Activity

Prepare a decision brief for offshore project portfolio prioritisation: knowledge check: scope, evidence, assumptions, hazards, safeguards, owner, decision gate and escalation trigger.

Assessment

Formative: 10-question practice quiz with answer feedback

Summative: Applied decision brief or practical case assessed against the rubric; proposed pass mark 70%, subject to academic approval.

Resources

Module 10: Offshore Project Portfolio Prioritisation: Competence Review

Learning objectives

Lessons

  1. Purpose and key terms of Offshore Project Portfolio Prioritisation: Competence Review
  2. Systems and operating context
  3. Evidence, assumptions and decision gates
  4. Hazards, safeguards and escalation
  5. Applied case: Offshore Project Portfolio Prioritisation

Teaching notes

## Teaching notes

Core explanation. Offshore Project Portfolio Prioritisation: Competence Review describes a practical part of Offshore Project Portfolio Prioritisation. Learners connect the principles to asset performance, people, operational risk, project value and local context.

Decision logic. Review the objective, evidence, limits, interfaces and applicable controls for offshore project portfolio prioritisation: competence review. Decisions require current information, role-appropriate authority, competent review and documented assumptions.

Worked example. Use an applied Namibia-relevant case in which a team plans offshore project portfolio prioritisation: competence review while balancing safety, integrity, schedule, cost, environmental protection and local capability.

Facilitator prompts. Ask learners to distinguish verified facts from assumptions, identify who has decision authority, name stop-work triggers and state what evidence could change their recommendation. Compare technical, HSE, commercial and community perspectives.

Activity. Prepare a decision brief for offshore project portfolio prioritisation: competence review: scope, evidence, assumptions, hazards, safeguards, owner, decision gate and escalation trigger.

Model answer guide. A sound response defines scope; uses current, traceable evidence; applies approved requirements and controls; records assumptions; assigns competent owners; checks interfaces; and communicates a measurable decision with an escalation path.

Assessment evidence. Score accuracy (30%), use of evidence (20%), safeguards (20%), analysis (20%) and communication (10%).

Activity

Prepare a decision brief for offshore project portfolio prioritisation: competence review: scope, evidence, assumptions, hazards, safeguards, owner, decision gate and escalation trigger.

Assessment

Formative: 10-question practice quiz with answer feedback

Summative: Applied decision brief or practical case assessed against the rubric; proposed pass mark 70%, subject to academic approval.

Resources

Draft learning content for review. This page does not represent accreditation or an external certificate. Confirm delivery, entry requirements and approval status with the Academy. Practice questions are generated drafts and require subject-matter review.